Two brand new JCB’s arrive

The first of two brand new JCB’s arrived today. These TLT 35-23D & 35-26D 4×4 STAGE V machines are designed for both fuel efficiency and heavy lifting. Thanks to Greenshields JCB Limited for a good service as usual.

Ecogen Recycling

We’ve Moved!

The Ecogen team is pleased to announce that we have now moved to a much larger facility in Kings Worthy Business Park, Winchester

New site development update 23/06/2020

New site development update 23/06/2020

Here is a snapshot of progress at Kings Worthy Business Park. Including: Gravel being laid, roof lanterns being constructed, ecology bird and bat box installation, the first of three baler conveyors installed, office cladding, speed humps.

New site development update 22/05/20

Progress is coming thick and fast as we enter the last phase of construction at Kings Worthy Business Park. The last slabs of concrete are being laid, three baler pits have been dug ready for machinery to arrive and industrial doors are nearly complete.

New site development update 01/05/20

Carlton Civil Engineering and Harrison Industrial have been making great progress laying yet more concrete and erecting steelwork for the loading doors. Here are some images of the progress so far.

Ecogen New Office

Site Development Update

New site development update… These pictures show:1) Building K9 demolished.2) Works starting on refurbishing the ‘old egg packing house’ into our new head office.