The Ecogen team is pleased to announce that we have now moved to a much larger facility in Kings Worthy Business Park, Winchester
The Ecogen team is pleased to announce that we have now moved to a much larger facility in Kings Worthy Business Park, Winchester
In order to ramp up production and grow into our seven acre site we have decided to install this Presona LP100 automatic baler. This machine is installed alongside our LP65 and LP50 and takes our processing capability to around 60 tonnes per hour. It also gives us real redundancy in case of machinery breakdown, never
Here are some new site development pictures. A series of firsts for Ecogen this month; our first delivery of recyclables at kings Worthy, our first container loading, our first new Linde 4.5 tonne forktruck added to the fleet. Over the coming weeks we will be installing all three balers and a paper shredder then we
Here is a snapshot of progress at Kings Worthy Business Park. Including: Gravel being laid, roof lanterns being constructed, ecology bird and bat box installation, the first of three baler conveyors installed, office cladding, speed humps.
Progress is coming thick and fast as we enter the last phase of construction at Kings Worthy Business Park. The last slabs of concrete are being laid, three baler pits have been dug ready for machinery to arrive and industrial doors are nearly complete.
Carlton Civil Engineering and Harrison Industrial have been making great progress laying yet more concrete and erecting steelwork for the loading doors. Here are some images of the progress so far.
The first slab of concrete for our new service yard at Kings Worthy Business Park is laid today. Over 5350m2 of reinforced concrete will be laid over the next 40 days. Other photos show the drainage system being installed which will supply water to our EcoPonds, frames going in for roller shutter doors, and the
Groundworks at our new Kings Worthy Business Park site continue at pace. Carlton Civil Engineering Ltd are digging to reduce levels and installing our specially designed Ecoponds. These will harbour wildlife and reduce our ecological impact on the wider environment. As an added benefit the ponds allow 100% of the sites surface water be attenuated
Ecogen are excited to announce that we have ordered a third baler for our new site which is under construction at Kings Worthy Business Park. This Presona LP100 CH2 baler will be added to our existing roster of two other Presona machines. We love a pre-press baler. Savings of up to 60% in energy versus
Ecogen Recycling Invest in a third Presona baler Read More »
We are delighted to announce that this week we have broken ground at Kings Worthy Business Park. This phase of construction will include; five acres of surfacing, installation of loading doors, installation of weighbridge and re-cladding the main office. Once complete we expect to be operational sometime in June.