Kings Worthy construction update 09/04/2020

The first slab of concrete for our new service yard at Kings Worthy Business Park is laid today. Over 5350m2 of reinforced concrete will be laid over the next 40 days. Other photos show the drainage system being installed which will supply water to our EcoPonds, frames going in for roller shutter doors, and the refurbishment of our staff facilities ready for our dedicated workforce.